Draft a defensible construction change order with entitlement basis, scope delta, itemised pricing, and schedule impact

Install / Use

npx skills add mohitagw15856/pm-claude-skills --skill change-order-writer

Installs into whichever agent you are using.

About this skill
📄

SKILL.md

Installable skill definition

Quality Score

79/100

Category

Legal

Supported Platforms

Universal

Our assessment of change-order-writer

change-order-writer scores 79/100 on our quality scale, 143rd of 177 Legal skills we index.

Its SKILL.md is 5.6 KB long, well organised into 8 sections and no code examples: a solid amount of guidance for an agent.

With 1,396 GitHub stars, it is one of the more widely adopted skills in the catalogue.

Substance
26/30
Structure
13/20
Description
12/15
Adoption
13/20
Freshness
15/15

Maintenance, license and trust

  • The repository was last updated 6 days ago, so change-order-writer is actively maintained.
  • It is released under the MIT license, a permissive license that allows use, modification and commercial use with attribution.
  • Its trust signals score 100/100, with no cautions. These come from repository metadata, not a code audit — read the skill file before letting an agent act on it.

change-order-writer compared with similar skills

All 4 of these similar skills score higher than change-order-writer; compare them before choosing.

SkillScoreStarsUpdatedFormat
change-order-writer (this skill)by mohitagw15856791.4k6d agoSKILL.md
algorithmic-artby anthropics100177.9k8d agoSKILL.md
pptxby anthropics100177.9k8d agoSKILL.md
designby nextlevelbuilder100130.2k9d agoSKILL.md
ui-ux-pro-maxby nextlevelbuilder100130.2k9d agoSKILL.md

Frequently asked questions

How do I install change-order-writer?
Run npx skills add mohitagw15856/pm-claude-skills --skill change-order-writer. The install tabs above show the steps for each supported agent.
Which AI agents does change-order-writer work with?
It is written for Universal, as a SKILL.md file. Other agents that read the same format can often use it too.
Is change-order-writer safe to use?
It is MIT-licensed and scores 100/100 on trust signals. Skills are instructions an agent will follow, so read the file before installing it and do not approve commands you do not understand.
Is change-order-writer still maintained?
The repository was last updated 6 days ago, so change-order-writer is actively maintained.

name: change-order-writer description: "Draft a defensible construction change order with entitlement basis, scope delta, itemised pricing, and schedule impact. Use when asked to write a change order, price extra work, draft a CO or COR/PCO, respond to a directive for changed work, or paper a field change. Produces a complete change order request with contract-clause entitlement, labour/material/equipment/OH&P breakdown, time impact statement, and reservation of rights."

Change Order Writer Skill

A change order that just says "extra work — $48,500" gets cut in half in review. A defensible one answers three questions before they're asked: why am I entitled (which contract clause, triggered by what event), what exactly changed (scope delta from the contract baseline), and what does it really cost (built-up pricing plus time). This skill drafts change orders that survive an owner's rep audit — and preserves rights on the impacts you can't price yet.

What This Skill Produces

  • A complete change order request (COR/PCO) ready for letterhead
  • Entitlement narrative citing the contract clause and the triggering event/document
  • Scope delta — contract baseline vs. changed condition, with document references
  • Pricing breakdown: labour, material, equipment, subcontractor cost, then OH&P per the contract markup provisions
  • Schedule impact statement and a reservation of rights for cumulative/unquantified impacts

Required Inputs

Ask for what's missing; from a thin brief, draft anyway and mark every gap [confirm]:

  • The change event — what happened (RFI answer, design revision, differing site condition, owner directive, regulatory change) and when it was discovered
  • Contract references — changes clause number, notice requirements, allowed markup percentages, unit rates if any
  • Baseline scope — what the contract documents required before the change
  • Cost inputs — crew composition, hours, material quantities/quotes, equipment, sub quotes (rough is fine; the skill structures them)
  • Schedule situation — is affected work on or near the critical path; current completion date

Entitlement & Pricing Framework

Entitlement first. Classify the trigger — it drives the clause you cite:

| Trigger | Typical basis | |---|---| | Owner/architect directive or design revision | Changes clause (e.g. AIA A201 §7 / EJCDC / contract equivalent) | | Differing site condition | DSC clause — Type I (differs from documents) or Type II (unusual for the locality) | | RFI answer adding work | Changes clause via the RFI/ASI as the directive document | | Owner-caused delay/interference | Changes + delay provisions (pair with a delay notice) |

Never assert entitlement without naming the clause and the triggering document by number and date. If notice deadlines have passed, say so and frame the submission accordingly — don't hide it.

Pricing build-up. Price from records, not round numbers: labour (crew × hours × loaded rates — base plus burden), material (quantities × quoted prices, attach quotes), equipment (owned at established rates, rented at invoice), subcontractor cost, then apply OH&P at the contract-specified markups on self-performed and sub work separately. Include small-tools/consumables, supervision, and bond/insurance adjustment if the contract allows. Anything estimated rather than quoted gets labelled.

Time. State added work duration and whether it hits the critical path. If time impact can't be fixed yet, request a to-be-determined extension and reserve rights — never write "no schedule impact" as a default.

Output Format

Change Order Request No. [#]: [Short title]

Project / Contract No. / Date / To / From 1. Description of change — plain-language summary of the changed condition. 2. Entitlement — clause citation + triggering document (RFI #, ASI #, directive, DSC discovery date) + notice given (date, method). 3. Scope delta — was/is table against contract documents. 4. Pricing — itemised table: Labour / Material / Equipment / Subcontractors / Subtotal / OH&P (per §[x]) / Bond & insurance / Total. Attachments list (quotes, tickets, T&M sheets). 5. Schedule impact — [X] calendar days requested, critical-path basis stated, or expressly reserved pending analysis. 6. Reservation of rights — rights reserved for cumulative impact, acceleration, and consequential effects not quantifiable at submission. 7. Signature block and the line: "This draft is not legal advice — route through your contracts counsel before sending."

Quality Checks

  • [ ] Entitlement cites a specific clause number and a specific triggering document with date
  • [ ] Notice status is stated honestly — given on time, late, or being given by this submission
  • [ ] Every cost line is either backed by a record/quote or labelled as an estimate [confirm]
  • [ ] OH&P follows the contract markup provisions, not a default percentage
  • [ ] Schedule impact is affirmatively stated or expressly reserved — never silent
  • [ ] Reservation of rights and the not-legal-advice routing line are present

Anti-Patterns

  • [ ] Do not price a change order from bare cost without OH&P and a cumulative-impact reservation — you won't get a second bite
  • [ ] Do not write "no schedule impact" reflexively to look cooperative — silence waives time you may need
  • [ ] Do not proceed with changed work on a verbal directive without papering it the same day
  • [ ] Do not bundle unrelated changes into one CO — each event stands on its own entitlement
  • [ ] Do not soften entitlement language ("we feel", "we believe we may be due") — state the clause and the facts

Related Skills

View on GitHub
GitHub Stars1.4k
CategoryLegal
Updated6d ago
Forks249

Languages

HTML

Trust signals

100/100

From repository metadata: license, adoption, age and documentation. Not a code audit — see the Safety scan above for what the skill file itself contains.

No cautions