cwicr-schedule-integrator
Integrate CWICR cost data with project schedules. Link work items to schedule activities, generate cost-loaded schedules, and cash flow projections.
Install / Use
npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill cwicr-schedule-integratorInstalls into whichever agent you are using.
SKILL.md
Installable skill definition
Quality Score
Category
Development & EngineeringSupported Platforms
Our assessment of cwicr-schedule-integrator
cwicr-schedule-integrator scores 91/100 on our quality scale, 1210th of 4,716 Development & Engineering skills we index (top 26%).
Its SKILL.md is 15 KB long, well organised into 16 sections with 5 code examples: a thorough specification that gives an agent plenty to work with.
It has 333 GitHub stars, a meaningful sign that others use it.
Maintenance, license and trust
- The repository was last updated about 3 months ago, so cwicr-schedule-integrator is actively maintained.
- Our last check on 2026-11-20 found the source still online.
- It is released under the MIT license, a permissive license that allows use, modification and commercial use with attribution.
- Its trust signals score 100/100, with no cautions. These come from repository metadata, not a code audit — read the skill file before letting an agent act on it.
Safety scan
No issues foundOur scan of the whole file found no instruction hijacking, hidden characters, credential access, data exfiltration or destructive commands. An AI review of the same text found nothing harmful.
AI review by kimi-k2.7-code on 2026-10-06. Automated pattern scan on 2026-10-05. It catches known dangerous patterns, not every risk — read a skill before letting an agent act on it.
cwicr-schedule-integrator compared with similar skills
All 4 of these similar skills score higher than cwicr-schedule-integrator; compare them before choosing.
| Skill | Score | Stars | Updated | Format |
|---|---|---|---|---|
| cwicr-schedule-integrator (this skill)by datadrivenconstruction | 91 | 333 | 3mo ago | SKILL.md |
| taste-skillby Leonxlnx | 100 | 118.9k | 11d ago | CLAUDE.md |
| Agent-Reachby Panniantong | 100 | 113.3k | 12d ago | CLAUDE.md |
| hyperframesby heygen-com | 100 | 87.1k | today | CLAUDE.md |
| headroomby headroomlabs-ai | 100 | 80.2k | today | CLAUDE.md |
Frequently asked questions
- How do I install cwicr-schedule-integrator?
- Run
npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill cwicr-schedule-integrator. The install tabs above show the steps for each supported agent. - Which AI agents does cwicr-schedule-integrator work with?
- It is written for Universal, as a SKILL.md file. Other agents that read the same format can often use it too.
- Is cwicr-schedule-integrator safe to use?
- Our scan of the whole file found no instruction hijacking, hidden characters, credential access, data exfiltration or destructive commands. An AI review of the same text found nothing harmful. It is MIT-licensed and scores 100/100 on trust signals. Skills are instructions an agent will follow, so read the file before installing it and do not approve commands you do not understand.
- Is cwicr-schedule-integrator still maintained?
- The repository was last updated about 3 months ago, so cwicr-schedule-integrator is actively maintained.
Skill content
View source on GitHubname: "cwicr-schedule-integrator" description: "Integrate CWICR cost data with project schedules. Link work items to schedule activities, generate cost-loaded schedules, and cash flow projections." homepage: "https://datadrivenconstruction.io" metadata: {"openclaw": {"emoji": "🗄️", "os": ["darwin", "linux", "win32"], "homepage": "https://datadrivenconstruction.io", "requires": {"bins": ["python3"]}}}
CWICR Schedule Integrator
Business Case
Problem Statement
Project planning requires:
- Linking costs to schedule activities
- Generating cost-loaded schedules
- Projecting cash flow requirements
- Tracking earned value
Solution
Integrate CWICR cost data with project schedules to create cost-loaded Gantt charts, cash flow curves, and earned value tracking.
Business Value
- Cost visibility - See when costs occur
- Cash flow - Project funding requirements
- Earned value - Track cost/schedule performance
- Integration - Connect cost and schedule data
Technical Implementation
import pandas as pd
import numpy as np
from typing import Dict, Any, List, Optional, Tuple
from dataclasses import dataclass, field
from datetime import datetime, timedelta, date
from enum import Enum
from collections import defaultdict
class CostDistribution(Enum):
"""Methods for distributing costs over time."""
UNIFORM = "uniform" # Even distribution
FRONT_LOADED = "front_loaded" # More at start
BACK_LOADED = "back_loaded" # More at end
S_CURVE = "s_curve" # S-curve distribution
@dataclass
class ScheduleActivity:
"""Project schedule activity."""
activity_id: str
description: str
start_date: date
end_date: date
duration_days: int
work_items: List[str]
budgeted_cost: float
predecessors: List[str] = field(default_factory=list)
@dataclass
class CostLoadedActivity:
"""Activity with daily cost distribution."""
activity: ScheduleActivity
daily_costs: Dict[date, float]
cumulative_costs: Dict[date, float]
@dataclass
class CashFlowProjection:
"""Cash flow projection."""
project_name: str
start_date: date
end_date: date
total_cost: float
daily_costs: Dict[date, float]
weekly_costs: Dict[str, float]
monthly_costs: Dict[str, float]
cumulative: Dict[date, float]
@dataclass
class EarnedValueMetrics:
"""Earned value metrics at point in time."""
data_date: date
planned_value: float # PV / BCWS
earned_value: float # EV / BCWP
actual_cost: float # AC / ACWP
schedule_variance: float # SV = EV - PV
cost_variance: float # CV = EV - AC
spi: float # Schedule Performance Index
cpi: float # Cost Performance Index
eac: float # Estimate at Completion
etc: float # Estimate to Complete
class CWICRScheduleIntegrator:
"""Integrate CWICR costs with project schedules."""
def __init__(self, cwicr_data: pd.DataFrame):
self.cost_data = cwicr_data
self._index_data()
def _index_data(self):
"""Index cost data."""
if 'work_item_code' in self.cost_data.columns:
self._code_index = self.cost_data.set_index('work_item_code')
else:
self._code_index = None
def get_work_item_cost(self, code: str, quantity: float) -> float:
"""Get total cost for work item."""
if self._code_index is None or code not in self._code_index.index:
return 0
item = self._code_index.loc[code]
labor = float(item.get('labor_cost', 0) or 0)
material = float(item.get('material_cost', 0) or 0)
equipment = float(item.get('equipment_cost', 0) or 0)
return (labor + material + equipment) * quantity
def create_schedule_activity(self,
activity_id: str,
description: str,
start_date: date,
duration_days: int,
work_items: List[Dict[str, Any]],
predecessors: List[str] = None) -> ScheduleActivity:
"""Create schedule activity with linked work items."""
# Calculate budgeted cost
total_cost = 0
codes = []
for item in work_items:
code = item.get('work_item_code', item.get('code'))
qty = item.get('quantity', 0)
total_cost += self.get_work_item_cost(code, qty)
codes.append(code)
end_date = start_date + timedelta(days=duration_days)
return ScheduleActivity(
activity_id=activity_id,
description=description,
start_date=start_date,
end_date=end_date,
duration_days=duration_days,
work_items=codes,
budgeted_cost=round(total_cost, 2),
predecessors=predecessors or []
)
def distribute_cost(self,
activity: ScheduleActivity,
method: CostDistribution = CostDistribution.UNIFORM) -> CostLoadedActivity:
"""Distribute activity cost over duration."""
daily_costs = {}
days = activity.duration_days
if days == 0:
daily_costs[activity.start_date] = activity.budgeted_cost
else:
if method == CostDistribution.UNIFORM:
daily_amount = activity.budgeted_cost / days
for i in range(days):
day = activity.start_date + timedelta(days=i)
daily_costs[day] = daily_amount
elif method == CostDistribution.FRONT_LOADED:
# Higher at start, decreasing
total_weight = sum(range(days, 0, -1))
for i in range(days):
day = activity.start_date + timedelta(days=i)
weight = (days - i) / total_weight
daily_costs[day] = activity.budgeted_cost * weight
elif method == CostDistribution.BACK_LOADED:
# Lower at start, increasing
total_weight = sum(range(1, days + 1))
for i in range(days):
day = activity.start_date + timedelta(days=i)
weight = (i + 1) / total_weight
daily_costs[day] = activity.budgeted_cost * weight
elif method == CostDistribution.S_CURVE:
# S-curve distribution (sigmoid)
for i in range(days):
day = activity.start_date + timedelta(days=i)
# Sigmoid function normalized
x = (i / days - 0.5) * 10
sigmoid = 1 / (1 + np.exp(-x))
daily_costs[day] = activity.budgeted_cost * sigmoid / days * 2
# Calculate cumulative
cumulative = {}
running_total = 0
for day in sorted(daily_costs.keys()):
running_total += daily_costs[day]
cumulative[day] = running_total
return CostLoadedActivity(
activity=activity,
daily_costs=daily_costs,
cumulative_costs=cumulative
)
def generate_cash_flow(self,
activities: List[ScheduleActivity],
project_name: str = "Project",
distribution: CostDistribution = CostDistribution.S_CURVE) -> CashFlowProjection:
"""Generate project cash flow projection."""
# Distribute costs for all activities
loaded_activities = [
self.distribute_cost(a, distribution)
for a in activities
]
# Aggregate daily costs
daily_costs = defaultdict(float)
for loaded in loaded_activities:
for day, cost in loaded.daily_costs.items():
daily_costs[day] += cost
# Sort and calculate cumulative
sorted_days = sorted(daily_costs.keys())
cumulative = {}
running_total = 0
for day in sorted_days:
running_total += daily_costs[day]
cumulative[day] = running_total
# Aggregate to weekly
weekly_costs = defaultdict(float)
for day, cost in daily_costs.items():
week_key = day.strftime('%Y-W%W')
weekly_costs[week_key] += cost
# Aggregate to monthly
monthly_costs = defaultdict(float)
for day, cost in daily_costs.items():
month_key = day.strftime('%Y-%m')
monthly_costs[month_key] += cost
return CashFlowProjection(
project_name=project_name,
start_date=min(daily_costs.keys()) if daily_costs else date.today(),
end_date=max(daily_costs.keys()) if daily_costs else date.today(),
total_cost=sum(daily_costs.values()),
daily_costs=dict(daily_costs),
weekly_costs=dict(weekly_costs),
monthly_costs=dict(monthly_costs),
cumulative=cumulative
)
def calculate_earned_value(self,
activities: List[ScheduleActivity],
progress: Dict[str, float], # activity_id -> percent complete
actual_costs: Dict[str, float], # activity_id -> actual cost
data_date: date) -> EarnedValueMetrics:
"""Calculate earned value metrics."""
# Generate planned value curve
cash_flow = self.generate_cash_flow(activities)
# Planned Value (BCWS) - budgeted cost through data date
pv = sum(
cost for day, cost in cash_flow.daily_costs.items()
if day <= data_date
)
# Earned Value (BCWP) - budgeted cost * percent complete
ev = sum(
a.budgeted_cost * progress.get(a.activity_id, 0) / 100
for a in activities
)
# Actual Cost (ACWP)
ac = sum(actual_costs.values())
# Variances
sv = ev - pv
cv = ev - ac
# Indices
spi = ev / pv if pv > 0 else 0
cpi = ev / ac if ac > 0 else 0
# Estimate at completion
bac = sum(a.budgeted_cost for a in activities)
if cpi > 0:
eac = bac / cpi
else:
eac = bac
etc = eac - ac
return EarnedValueMetrics(
data_date=data_date,
planned_value=round(pv, 2),
earned_value=round(ev, 2),
actual_cost=round(ac, 2),
schedule_variance=round(sv, 2),
cost_variance=round(cv, 2),
spi=round(spi, 2),
cpi=round(cpi, 2),
eac=round(eac, 2),
etc=round(etc, 2)
)
def export_cash_flow(self,
cash_flow: CashFlowProjection,
output_path: str) -> str:
"""Export cash flow to Excel."""
with pd.ExcelWriter(output_path, engine='openpyxl') as writer:
# Summary
summary_df = pd.DataFrame([{
'Project': cash_flow.project_name,
'Start Date': cash_flow.start_date,
'End Date': cash_flow.end_date,
'Total Cost': cash_flow.total_cost
}])
summary_df.to_excel(writer, sheet_name='Summary', index=False)
# Monthly
monthly_df = pd.DataFrame([
{'Month': month, 'Cost': cost}
for month, cost in sorted(cash_flow.monthly_costs.items())
])
monthly_df.to_excel(writer, sheet_name='Monthly', index=False)
# Weekly
weekly_df = pd.DataFrame([
{'Week': week, 'Cost': cost}
for week, cost in sorted(cash_flow.weekly_costs.items())
])
weekly_df.to_excel(writer, sheet_name='Weekly', index=False)
# Daily with c
Truncated for display — read the full file on GitHub.
Related Skills
taste-skill
118.9kAgent skills that give coding agents taste: art direction, reference images and a browser check instead of generic AI pages
Agent-Reach
113.3kGive your AI agent eyes to see the entire internet. Read & search Twitter, Reddit, YouTube, GitHub, Bilibili, XiaoHongShu — one CLI, zero API fees.
hyperframes
87.1kAI video you can actually edit. HyperFrames is a free, open-source AI video editor. Describe any video and get a real project you can change down to the frame.
headroom
80.2kCompress tool outputs, logs, files, and RAG chunks before they reach the LLM. 20% fewer tokens for coding agents, 60-95% fewer tokens for JSON, same answers. Library, proxy, MCP server.
Languages
Trust signals
From repository metadata: license, adoption, age and documentation. Not a code audit — see the Safety scan above for what the skill file itself contains.