critical-path-analyzer
Analyze project critical path from schedule data. Identify critical activities, calculate float, and assess schedule risk.
Install / Use
npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill critical-path-analyzerInstalls into whichever agent you are using.
SKILL.md
Installable skill definition
Quality Score
Category
Development & EngineeringSupported Platforms
Our assessment of critical-path-analyzer
critical-path-analyzer scores 91/100 on our quality scale, 1299th of 4,601 Development & Engineering skills we index (top 29%).
Its SKILL.md is 12 KB long, well organised into 14 sections with 5 code examples: a thorough specification that gives an agent plenty to work with.
It has 333 GitHub stars, a meaningful sign that others use it.
Maintenance, license and trust
- The repository was last updated about 2 months ago, so critical-path-analyzer is actively maintained.
- It is released under the MIT license, a permissive license that allows use, modification and commercial use with attribution.
- Its trust signals score 100/100, with no cautions. These come from repository metadata, not a code audit — read the skill file before letting an agent act on it.
critical-path-analyzer compared with similar skills
All 4 of these similar skills score higher than critical-path-analyzer; compare them before choosing.
| Skill | Score | Stars | Updated | Format |
|---|---|---|---|---|
| critical-path-analyzer (this skill)by datadrivenconstruction | 91 | 333 | 56d ago | SKILL.md |
| Agent-Reachby Panniantong | 100 | 98.3k | 2d ago | CLAUDE.md |
| taste-skillby Leonxlnx | 100 | 98.1k | 2d ago | CLAUDE.md |
| headroomby headroomlabs-ai | 100 | 75.5k | today | CLAUDE.md |
| ai-job-searchby MadsLorentzen | 100 | 48.8k | 1d ago | CLAUDE.md |
Frequently asked questions
- How do I install critical-path-analyzer?
- Run
npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill critical-path-analyzer. The install tabs above show the steps for each supported agent. - Which AI agents does critical-path-analyzer work with?
- It is written for Universal, as a SKILL.md file. Other agents that read the same format can often use it too.
- Is critical-path-analyzer safe to use?
- It is MIT-licensed and scores 100/100 on trust signals. Skills are instructions an agent will follow, so read the file before installing it and do not approve commands you do not understand.
- Is critical-path-analyzer still maintained?
- The repository was last updated about 2 months ago, so critical-path-analyzer is actively maintained.
Skill content
View source on GitHubname: "critical-path-analyzer" description: "Analyze project critical path from schedule data. Identify critical activities, calculate float, and assess schedule risk." homepage: "https://datadrivenconstruction.io" metadata: {"openclaw": {"emoji": "📅", "os": ["darwin", "linux", "win32"], "homepage": "https://datadrivenconstruction.io", "requires": {"bins": ["python3"]}}}
Critical Path Analyzer
Business Case
Problem Statement
Schedule management requires understanding:
- Which activities are critical?
- How much float exists?
- What delays impact completion?
- Where to focus resources?
Solution
Analyze schedule network to identify critical path, calculate float, and provide actionable schedule insights.
Technical Implementation
import pandas as pd
import numpy as np
from typing import Dict, Any, List, Optional, Set
from dataclasses import dataclass, field
from datetime import date, timedelta
from enum import Enum
from collections import defaultdict
class ActivityStatus(Enum):
NOT_STARTED = "not_started"
IN_PROGRESS = "in_progress"
COMPLETED = "completed"
DELAYED = "delayed"
@dataclass
class Activity:
activity_id: str
name: str
duration: int # days
predecessors: List[str]
early_start: int = 0
early_finish: int = 0
late_start: int = 0
late_finish: int = 0
total_float: int = 0
free_float: int = 0
is_critical: bool = False
status: ActivityStatus = ActivityStatus.NOT_STARTED
percent_complete: float = 0
actual_start: Optional[date] = None
actual_finish: Optional[date] = None
@dataclass
class CriticalPathResult:
critical_path: List[str]
project_duration: int
activities: Dict[str, Activity]
near_critical: List[str] # Float < 5 days
total_float_days: int
class CriticalPathAnalyzer:
"""Analyze project critical path."""
NEAR_CRITICAL_THRESHOLD = 5 # days
def __init__(self, project_start: date):
self.project_start = project_start
self.activities: Dict[str, Activity] = {}
def add_activity(self,
activity_id: str,
name: str,
duration: int,
predecessors: List[str] = None):
"""Add activity to network."""
self.activities[activity_id] = Activity(
activity_id=activity_id,
name=name,
duration=duration,
predecessors=predecessors or []
)
def import_from_dataframe(self, df: pd.DataFrame):
"""Import activities from DataFrame."""
for _, row in df.iterrows():
preds = row.get('predecessors', '')
if pd.isna(preds):
pred_list = []
else:
pred_list = [p.strip() for p in str(preds).split(',') if p.strip()]
self.add_activity(
activity_id=str(row['activity_id']),
name=row['name'],
duration=int(row['duration']),
predecessors=pred_list
)
def _forward_pass(self):
"""Calculate early start and early finish (forward pass)."""
# Topological sort
sorted_activities = self._topological_sort()
for activity_id in sorted_activities:
activity = self.activities[activity_id]
# Early start = max(early finish of all predecessors)
if not activity.predecessors:
activity.early_start = 0
else:
activity.early_start = max(
self.activities[pred].early_finish
for pred in activity.predecessors
if pred in self.activities
)
activity.early_finish = activity.early_start + activity.duration
def _backward_pass(self):
"""Calculate late start and late finish (backward pass)."""
# Find project duration
project_duration = max(a.early_finish for a in self.activities.values())
# Build successors map
successors = defaultdict(list)
for activity_id, activity in self.activities.items():
for pred in activity.predecessors:
if pred in self.activities:
successors[pred].append(activity_id)
# Reverse topological order
sorted_activities = self._topological_sort()[::-1]
for activity_id in sorted_activities:
activity = self.activities[activity_id]
# Late finish = min(late start of all successors)
if activity_id not in successors or not successors[activity_id]:
activity.late_finish = project_duration
else:
activity.late_finish = min(
self.activities[succ].late_start
for succ in successors[activity_id]
)
activity.late_start = activity.late_finish - activity.duration
# Calculate floats
activity.total_float = activity.late_start - activity.early_start
activity.is_critical = activity.total_float == 0
def _topological_sort(self) -> List[str]:
"""Topological sort of activities."""
visited = set()
result = []
def visit(activity_id: str):
if activity_id in visited:
return
visited.add(activity_id)
activity = self.activities.get(activity_id)
if activity:
for pred in activity.predecessors:
if pred in self.activities:
visit(pred)
result.append(activity_id)
for activity_id in self.activities:
visit(activity_id)
return result
def calculate_critical_path(self) -> CriticalPathResult:
"""Calculate critical path and all float values."""
self._forward_pass()
self._backward_pass()
# Find critical path
critical_activities = [
a.activity_id for a in self.activities.values()
if a.is_critical
]
# Near-critical activities
near_critical = [
a.activity_id for a in self.activities.values()
if 0 < a.total_float <= self.NEAR_CRITICAL_THRESHOLD
]
project_duration = max(a.early_finish for a in self.activities.values())
total_float = sum(a.total_float for a in self.activities.values())
return CriticalPathResult(
critical_path=critical_activities,
project_duration=project_duration,
activities=self.activities,
near_critical=near_critical,
total_float_days=total_float
)
def get_schedule_dates(self) -> pd.DataFrame:
"""Get schedule with dates."""
data = []
for activity in self.activities.values():
early_start_date = self.project_start + timedelta(days=activity.early_start)
early_finish_date = self.project_start + timedelta(days=activity.early_finish)
late_start_date = self.project_start + timedelta(days=activity.late_start)
late_finish_date = self.project_start + timedelta(days=activity.late_finish)
data.append({
'Activity ID': activity.activity_id,
'Name': activity.name,
'Duration': activity.duration,
'Early Start': early_start_date,
'Early Finish': early_finish_date,
'Late Start': late_start_date,
'Late Finish': late_finish_date,
'Total Float': activity.total_float,
'Critical': 'Yes' if activity.is_critical else 'No'
})
return pd.DataFrame(data)
def analyze_delay_impact(self,
activity_id: str,
delay_days: int) -> Dict[str, Any]:
"""Analyze impact of delay on project."""
activity = self.activities.get(activity_id)
if not activity:
return {}
absorbed_by_float = min(delay_days, activity.total_float)
project_delay = max(0, delay_days - activity.total_float)
# Find affected activities
affected = []
if project_delay > 0:
# Activities that could be affected (successors)
for a in self.activities.values():
if activity_id in a.predecessors:
affected.append(a.activity_id)
return {
'activity': activity_id,
'delay_days': delay_days,
'available_float': activity.total_float,
'absorbed_by_float': absorbed_by_float,
'project_delay': project_delay,
'affected_activities': affected,
'is_critical_delay': project_delay > 0
}
def suggest_acceleration(self,
target_reduction: int) -> List[Dict[str, Any]]:
"""Suggest activities to accelerate to meet target."""
result = self.calculate_critical_path()
suggestions = []
# Focus on critical activities
for activity_id in result.critical_path:
activity = self.activities[activity_id]
# Assume can reduce by 20% max
max_reduction = int(activity.duration * 0.2)
if max_reduction > 0:
suggestions.append({
'activity': activity_id,
'name': activity.name,
'current_duration': activity.duration,
'max_reduction': max_reduction,
'reason': 'Critical path activity'
})
# Sort by potential impact
return sorted(suggestions, key=lambda x: x['max_reduction'], reverse=True)
def export_analysis(self, output_path: str) -> str:
"""Export analysis to Excel."""
result = self.calculate_critical_path()
with pd.ExcelWriter(output_path, engine='openpyxl') as writer:
# Summary
summary_df = pd.DataFrame([{
'Project Start': self.project_start,
'Project Duration': result.project_duration,
'Project Finish': self.project_start + timedelta(days=result.project_duration),
'Critical Activities': len(result.critical_path),
'Near-Critical Activities': len(result.near_critical),
'Total Float (days)': result.total_float_days
}])
summary_df.to_excel(writer, sheet_name='Summary', index=False)
# Schedule
schedule_df = self.get_schedule_dates()
schedule_df.to_excel(writer, sheet_name='Schedule', index=False)
# Critical Path
critical_df = pd.DataFrame([
{
'Activity': a_id,
'Name': self.activities[a_id].name,
'Duration': self.activities[a_id].duration
}
for a_id in result.critical_path
])
critical_df.to_excel(writer, sheet_name='Critical Path', index=False)
return output_path
Quick Start
from datetime import date
# Initialize analyzer
analyzer = CriticalPathAnalyzer(project_start=date(2024, 6, 1))
# Add activities
analyzer.add_activity("A", "Site Preparation", 10, [])
analyzer.add_activity("B", "Foundation Excavation", 15, ["A"])
analyzer.add_activity("C", "Foundation Concrete", 20, ["B"])
analyzer.add_activity("D", "Structural Steel", 30, ["C"])
analyzer.add_activity("E", "MEP Rough-in", 25, ["C"])
analyzer.add_activity("F", "Exterior Walls", 20, ["D"])
analyzer.add_activity("G", "Interior Finish", 15, ["E", "F"])
# Calculate critical path
result = analyzer.calculate_critical_path()
print(f"Project Duration: {result.project_duration} days")
print(f"Critical Path: {result.critical_path}")
Common Use Cases
1. Analyze Delay Impact
impact = analyz
Truncated for display — read the full file on GitHub.
Related Skills
Agent-Reach
98.3kGive your AI agent eyes to see the entire internet. Read & search Twitter, Reddit, YouTube, GitHub, Bilibili, XiaoHongShu — one CLI, zero API fees.
taste-skill
98.1kAgent skills that give coding agents taste: art direction, reference images and a browser check instead of generic AI pages
headroom
75.5kCompress tool outputs, logs, files, and RAG chunks before they reach the LLM. 20% fewer tokens for coding agents, 60-95% fewer tokens for JSON, same answers. Library, proxy, MCP server.
ai-job-search
48.8kThe job search that runs on your machine. AI job application framework built on Claude Code: evaluate postings, tailor CVs, write cover letters, prep interviews. Fork it and own it.
Languages
Trust signals
From repository metadata: license, adoption, age and documentation. Not a code audit — see the Safety scan above for what the skill file itself contains.