afrexai-construction-estimator

Complete construction estimating and cost management system

Install / Use

npx skills add LeoYeAI/openclaw-master-skills --skill afrexai-construction-estimator

Installs into whichever agent you are using.

About this skill
๐Ÿ“„

SKILL.md

Installable skill definition

Quality Score

83/100

Category

Operations

Supported Platforms

Universal

Tags

Our assessment of afrexai-construction-estimator

afrexai-construction-estimator scores 83/100 on our quality scale, 602nd of 745 Operations skills we index.

Its SKILL.md is 24 KB long, well organised into 49 sections with 13 code examples: a thorough specification that gives an agent plenty to work with.

With 2,149 GitHub stars, it is one of the more widely adopted skills in the catalogue.

Substance
30/30
Structure
20/20
Description
8/15
Adoption
14/20
Freshness
11/15

Maintenance, license and trust

  • The repository was last updated about 4 months ago. That is recent enough to be usable, but agent tooling moves fast, so check the instructions against your agent's current version.
  • Our last check on 2026-11-07 found the source still online.
  • It is released under the MIT license, a permissive license that allows use, modification and commercial use with attribution.
  • Its trust signals score 98/100, with no cautions. These come from repository metadata, not a code audit โ€” read the skill file before letting an agent act on it.

Safety scan

No issues found

Our scan of the whole file found no instruction hijacking, hidden characters, credential access, data exfiltration or destructive commands. An AI review of the same text found nothing harmful.

AI review by kimi-k2.7-code on 2026-10-01. Automated pattern scan on 2026-10-01. It catches known dangerous patterns, not every risk โ€” read a skill before letting an agent act on it.

afrexai-construction-estimator compared with similar skills

All 4 of these similar skills score higher than afrexai-construction-estimator; compare them before choosing.

SkillScoreStarsUpdatedFormat
afrexai-construction-estimator (this skill)by LeoYeAI832.1k4mo agoSKILL.md
x402by browser-use100121.0k3d agoSKILL.md
algorithmic-artby anthropics100177.9k55d agoSKILL.md
pptxby anthropics100177.9k55d agoSKILL.md
designby nextlevelbuilder100149.0k6d agoSKILL.md

Frequently asked questions

How do I install afrexai-construction-estimator?
Run npx skills add LeoYeAI/openclaw-master-skills --skill afrexai-construction-estimator. The install tabs above show the steps for each supported agent.
Which AI agents does afrexai-construction-estimator work with?
It is written for Universal, as a SKILL.md file. Other agents that read the same format can often use it too.
Is afrexai-construction-estimator safe to use?
Our scan of the whole file found no instruction hijacking, hidden characters, credential access, data exfiltration or destructive commands. An AI review of the same text found nothing harmful. It is MIT-licensed and scores 98/100 on trust signals. Skills are instructions an agent will follow, so read the file before installing it and do not approve commands you do not understand.
Is afrexai-construction-estimator still maintained?
The repository was last updated about 4 months ago. That is recent enough to be usable, but agent tooling moves fast, so check the instructions against your agent's current version.

name: afrexai-construction-estimator description: "Complete construction estimating and cost management system. Use when preparing project estimates, bid proposals, cost breakdowns, value engineering, change order management, or construction budget tracking. Covers residential, commercial, and infrastructure projects. Trigger on 'estimate', 'construction cost', 'bid', 'takeoff', 'cost breakdown', 'change order', 'value engineering', 'construction budget', 'unit pricing', 'RSMeans'."

Construction Estimator Pro

Complete construction estimating methodology โ€” from quantity takeoff to bid submission. Zero dependencies.


Phase 1: Project Classification & Estimate Type

Estimate Type Decision Matrix

| Project Stage | Estimate Type | Accuracy | Basis | Use Case | |---|---|---|---|---| | Concept | Order of Magnitude | -30% to +50% | SF/unit costs | Go/no-go decisions | | Schematic | Conceptual/Budget | -15% to +30% | Assembly costs | Budget approval | | Design Dev | Detailed | -10% to +15% | Quantity takeoff | GMP/bid preparation | | Construction Docs | Definitive/Bid | -5% to +10% | Full QTO + subs | Lump sum bid | | Construction | Control | Actual costs | Committed + forecast | Cost management |

Project Brief YAML

project:
  name: ""
  number: ""
  type: residential | commercial | industrial | infrastructure | renovation
  delivery: design-bid-build | design-build | CM-at-risk | IPD
  location:
    city: ""
    state: ""
    zip: ""
    location_factor: 1.00  # RSMeans city cost index / national average
  owner: ""
  architect: ""
  
scope:
  gross_sf: 0
  stories: 0
  site_acres: 0
  description: ""
  
schedule:
  bid_date: ""
  construction_start: ""
  substantial_completion: ""
  duration_months: 0
  
estimate:
  type: order-of-magnitude | conceptual | detailed | definitive
  base_date: ""  # Date costs are based on
  escalation_rate: 0.04  # Annual construction cost escalation
  
assumptions:
  - ""
exclusions:
  - ""
allowances:
  - item: ""
    amount: 0

Project Type Quick Reference

| Type | Key Considerations | Typical $/SF Range (2024-2026) | |---|---|---| | Single Family Residential | Foundation type, finishes grade, energy code | $150-$400/SF | | Multi-Family | Unit mix, parking ratio, amenities | $200-$450/SF | | Office (Class A) | Curtain wall, MEP density, TI allowance | $250-$550/SF | | Retail | Shell vs TI, storefront, grease traps | $150-$350/SF | | Healthcare/Hospital | Life safety, med gas, shielding | $400-$900/SF | | K-12 Education | Prevailing wage, hazmat, phasing | $300-$600/SF | | Warehouse/Distribution | Clear height, slab flatness, dock count | $80-$180/SF | | Hotel | Star rating drives finish, FF&E budget | $200-$500/SF | | Infrastructure (road/mile) | Soil conditions, utilities, traffic control | $2M-$10M/mile |


Phase 2: Quantity Takeoff (QTO)

CSI MasterFormat Division Structure

Use CSI MasterFormat 2018 for ALL estimates. Every line item maps to a division.

| Division | Name | Typical % of Total | |---|---|---| | 01 | General Requirements | 8-12% | | 02 | Existing Conditions | 1-5% | | 03 | Concrete | 8-15% | | 04 | Masonry | 2-6% | | 05 | Metals (Structural Steel) | 8-15% | | 06 | Wood, Plastics, Composites | 3-8% | | 07 | Thermal & Moisture Protection | 4-8% | | 08 | Openings (Doors/Windows) | 3-7% | | 09 | Finishes | 8-15% | | 10 | Specialties | 1-3% | | 11 | Equipment | 1-5% | | 12 | Furnishings | 1-5% | | 13 | Special Construction | 0-3% | | 14 | Conveying Equipment (Elevators) | 1-4% | | 21 | Fire Suppression | 2-4% | | 22 | Plumbing | 4-8% | | 23 | HVAC | 8-15% | | 26 | Electrical | 8-15% | | 27 | Communications | 1-3% | | 28 | Electronic Safety & Security | 1-3% | | 31 | Earthwork | 3-8% | | 32 | Exterior Improvements | 2-6% | | 33 | Utilities | 2-5% |

QTO Best Practices

  1. Measure twice, price once โ€” QTO errors cascade through the entire estimate
  2. Use consistent units โ€” SF for areas, LF for linear, CY for volume, EA for items
  3. Add waste factors by material:
    • Concrete: 5-8%
    • Masonry: 3-5%
    • Drywall: 10-12%
    • Roofing: 8-10%
    • Flooring (tile): 10-15%
    • Lumber: 8-10%
    • Rebar: 5-7%
    • Paint: 10-15%
  4. Document measurement methodology โ€” so anyone can verify
  5. Cross-check totals โ€” SF of drywall โ‰ˆ 2.5-3x floor area (both sides of walls + ceilings)

QTO Line Item Template

line_item:
  division: "03"
  spec_section: "03 30 00"
  description: "Cast-in-Place Concrete - Elevated Slabs"
  quantity: 450
  unit: CY
  unit_cost:
    labor: 85.00
    material: 165.00
    equipment: 25.00
    subcontractor: 0.00
  total_unit_cost: 275.00
  extended_cost: 123750.00
  waste_factor: 0.07
  adjusted_quantity: 481.5
  notes: "4500 PSI, #5 rebar @ 12\" OC EW, 6\" slab"
  source: "Sub quote - ABC Concrete (02/15/2026)"
  confidence: high | medium | low

Quantity Verification Cross-Checks

| Check | Formula | Flag If | |---|---|---| | Concrete per SF | Total CY รท Building SF | >0.15 CY/SF (unless heavy structure) | | Steel per SF | Total tons รท Building SF | >15 PSF (unless high-rise) | | Drywall SF | Total drywall SF รท Floor SF | <2.0 or >4.0 ratio | | Electrical per SF | Electrical $ รท Building SF | >$35/SF (standard office) | | Plumbing fixtures | Count vs occupancy | Missing fixtures for code compliance | | Parking spaces | Per local code requirements | Below minimum ratio |


Phase 3: Pricing & Cost Assembly

Unit Cost Development

Cost source hierarchy (most reliable first):

  1. Subcontractor quotes (3 minimum per trade) โ€” best for bid estimates
  2. Historical project data โ€” adjusted for location, time, scope
  3. RSMeans/Gordian data โ€” industry standard reference
  4. Vendor quotes โ€” for specific materials/equipment
  5. Published cost guides โ€” Marshall & Swift, Craftsman

Labor Cost Build-Up

labor_rate_build_up:
  trade: "Carpenter"
  base_wage: 42.50
  fringe_benefits: 18.75   # Health, pension, vacation, training
  payroll_taxes: 8.90      # FICA, FUTA, SUTA, workers comp
  total_burden: 27.65
  burdened_rate: 70.15
  
  productivity_factors:
    weather: 1.00           # 1.0 = normal, 1.15 = winter
    overtime: 1.00          # 1.0 = straight time, 1.5 = OT
    height: 1.00            # 1.0 = ground, 1.10 = >30ft
    congestion: 1.00        # 1.0 = open, 1.15 = tight
    shift: 1.00             # 1.0 = day, 1.10 = swing, 1.15 = night
  adjusted_rate: 70.15

Subcontractor Quote Evaluation

Score each sub quote (use minimum 3 per trade):

| Factor | Weight | 1-5 Score | |---|---|---| | Price competitiveness | 30% | | | Scope completeness (covers all spec sections?) | 25% | | | Qualifications/exclusions (red flags?) | 20% | | | Past performance/reputation | 15% | | | Bond capacity/insurance | 10% | | | Weighted Total | 100% | |

Red flags in sub quotes:

  • "As needed" or "TBD" line items (scope gap)
  • Short validity period (<30 days)
  • Unusual exclusions (e.g., electrician excluding wire)
  • No reference to spec sections
  • Price significantly below others (they missed something)

Crew Rate Assembly

Crew Daily Cost = ฮฃ(Workers ร— Daily Rate) + Equipment Daily Cost
Crew Daily Output = Units per 8-hour day (from labor standards)
Unit Cost = Crew Daily Cost รท Crew Daily Output

Example โ€” Concrete Placement Crew:

  • 1 Foreman @ $75/hr ร— 8 = $600
  • 4 Laborers @ $55/hr ร— 8 = $1,760
  • 1 Vibrator operator @ $60/hr ร— 8 = $480
  • Concrete pump (daily rental) = $1,200
  • Crew Daily Cost = $4,040
  • Daily output: 50 CY
  • Unit Labor+Equipment Cost = $80.80/CY
  • Material (concrete delivered) = $165/CY
  • Total in-place cost = $245.80/CY

Phase 4: Indirect Costs & Markups

General Conditions (Division 01) Checklist

| Item | Duration-Based? | Typical Range | |---|---|---| | Project Manager | Yes | $12K-$18K/month | | Superintendent | Yes | $10K-$16K/month | | Project Engineer | Yes | $8K-$12K/month | | Field Office (trailer) | Yes | $1K-$3K/month | | Temporary utilities | Yes | $2K-$5K/month | | Temporary toilets | Yes | $200-$500/month each | | Dumpsters/waste removal | Yes | $1K-$4K/month | | Safety equipment/supplies | Yes | $500-$2K/month | | Small tools & consumables | Lump | 1-2% of labor | | Final cleaning | Lump | $0.15-$0.50/SF | | Permits (building) | Lump | Varies by jurisdiction | | Insurance (Builder's Risk) | Lump | 0.5-1.5% of cost | | Performance/Payment Bond | Lump | 1-3% of contract | | Testing & inspection | Lump | 0.5-1.5% of cost | | As-built documentation | Lump | $5K-$25K | | Commissioning support | Lump | $10K-$50K |

Rule of thumb: General conditions = 8-15% of direct costs (lower for large projects, higher for small/complex).

Markup Stack

markup_calculation:
  direct_costs: 2500000
  
  general_conditions:
    percentage: 0.10
    amount: 250000
    
  subtotal_1: 2750000
  
  overhead:
    percentage: 0.05     # Home office overhead
    amount: 137500
    
  subtotal_2: 2887500
  
  profit:
    percentage: 0.05     # Varies by market/risk
    amount: 144375
    
  subtotal_3: 3031875
  
  contingency:
    design_contingency: 0.05    # For incomplete drawings
    construction_contingency: 0.03  # For unforeseen conditions
    amount: 242550
    
  bond:
    percentage: 0.015
    amount: 49118
    
  escalation:
    rate: 0.04           # Annual
    months_to_midpoint: 8
    amount: 88536
    
  total_estimate: 3412079
  cost_per_sf: 341.21    # For 10,000 SF building

Contingency Guide

| Estimate Type | Design Contingency | Construction Contingency | |---|---|---| | Order of Magnitude | 15-25% | 10-15% | | Conceptual | 10-15% | 5-10% | | Detailed | 3-8% | 3-5% | | Definitive/Bid | 0-3% | 2-3% |

Contingency is NOT profit padding. Track and justify every contingency draw.


Phase 5: Bid Preparation & Strategy

Bid/No-Bid Decision Scorecard

Score 1-5 for each (minimum 30 to bid):

| Factor | Weight | Score | |---|---|---| | Project type experience | 3x | | | Client relationship/history | 2x | | | Current workload capacity | 3x | | | Geographic fit | 2x | | | Profit potential | 3x | | | Competition level (fewer = better) | 2x | | | Risk profile (lower = better) | 3x | | | Schedule feasibility | 2x | | | Bonding capacity available | 2x | | | Weighted Total | /110 | |

Bid Day Checklist

48 hours before:

  • [ ] All sub quotes received (minimum 3 per trade)
  • [ ] All material quotes current (check expiration dates)
  • [ ] Addenda reviewed and incorporated (ALL of them)
  • [ ] Scope gaps identified and plugged
  • [ ] Math verified (independent check)

Day of bid:

  • [ ] Final sub quotes plugged in
  • [ ] Markup/profit decision finalized
  • [ ] Alternates priced if required
  • [ ] Unit prices calculated if required
  • [ ] Bid bond secured
  • [ ] Bid form completed correctly (every blank filled)
  • [ ] Acknowledge ALL addenda on bid form
  • [ ] Authorized signature
  • [ ] Delivered before deadline (allow 1+ hour buffer)

Competitive Bid Strategy

Market conditions affect markup:

  • Hot market (lots of work): Markup 8-12% (O&P combined)
  • Normal market: Markup 6-10%
  • Slow market: Markup 3-6%
  • Must-win/strategic: Markup 2-4% (minimum to cover overhead)

Bid spread analysis (track your results):

Bid Spread = (Your Bid - Low Bid) รท Low Bid ร— 100
  • Consistently >10% high โ†’ Your costs are inflated or productivity assumptions too conservative
  • Consistently <2% from low โ†’ You might be leaving money on the table
  • Target: Within 3-5% of winning bid

Phase 6: Value Engineering (VE)

VE Opportunity Matrix

| System | VE Opportunity | Typical Savings | Risk Level | |---|---|---|---| | Structural | Steel vs concrete frame | 5-15% of structure | Medium | | Foundations | Spread vs mat vs piles | 10-30% of foundation | High (geotech dependent) | | Envelope | Curtain wall vs storefront | 15-30% of facade | Low-Medium | | Roofing | TPO vs modified bitumen | 10-20% of

Truncated for display โ€” read the full file on GitHub.

Related Skills

View on GitHub
GitHub Stars2.1k
CategoryOperations
Updated3mo ago
Forks325

Languages

Python

Trust signals

98/100

From repository metadata: license, adoption, age and documentation. Not a code audit โ€” see the Safety scan above for what the skill file itself contains.

1 info
afrexai-construction-estimator โ€” Universal Skill: Install & Safety Check | SkillAgent